| UTILITIES |
| |
|
|
|
|
|
|
| B-06-30 |
LIME RESIDUALS HAULING AND DISPOSAL |
|
Approval Date: |
9/26/2006 |
| |
|
|
|
|
|
|
SCOPE: provides lime residuals hauling and disposal services for the following water treatment facilities: Lee County's Green Meadows Water Treatment Plant; Lee County's Waterway Water Treatment Plant; Lee County's College Parkway Water Treatment Plant
|
|
|
|
|
|
|
|
|
|
|
|
|
| Project Mgr: Hank Barroso |
|
|
|
|
| |
|
|
|
|
|
|
| Contract # |
CONTRACTOR: |
|
Contact Name & Number: |
|
NTP: |
10/19/2006 |
| 3656 |
Karle Enviro-Organic Recycling, Inc. |
Krish Alexander, 239.693.6600 |
|
Renewal Date: |
9/30/2008 |
| |
|
|
|
|
Final Exp Date: |
9/30/2011 |
| |
|
|
|
|
Contract Term: |
1 year |
| |
|
|
|
|
Renewals: |
4-1 year |
| |
|
|
|
|
|
|
| Bonding Information: |
|
The COUNTY will NOT require the Public Payment and Performance Bond on this project. |
| Additional Information: |
|
GREEN MEADOWS WTP $249,240.00 COLLEGE PARKWAY WTP $28,140.00 WATER WAY ESTATES $28,140.00
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|