June
26 through July 02, 2008 |
|
New Road Projects: |
|
 |
Summerlin Rd. from Cypress Lake to Boy Scout
Dr.
-
construction begins this week to widen Summerlin Rd. to 6
lanes and construct and overpass at College Pkwy. Utility
work, construction layout and installation of temporary
pavement in the median will get underway. Two travel lanes in
each directional will be maintained during daylight hours.
If you have any questions, please contact Sarah Clarke at
533-8718 |
 |
Coconut Road - The project to widen
Coconut Road west of US 41 began on February 11, 2008. Work to
include: re-alignment of the intersection at US 41, road
widening, and utility installation. The project is scheduled
to take 6 months. If you have any questions, please contact
Lou Wolodzko at 239/985-1200. |
 |
Corkscrew Road - Construction of a two-lane
curve at the eastern most portion of Corkscrew Road began January 7,
2008 and should last 6 months. If you have any
questions, please contact Eyra Cash at 239/533-8562. |
|
S.R. 78 and Littleton Road. This project is
scheduled to be completed within 60 days or the end of April
2008. Lane closures and traffic impacts may occur but will be
minimal.
If you have any questions please contact
Bob Debrock at Lee County DOT Operations 694-3334 |
|
Construction on
Gunnery Road from SR 82 to Lee Blvd began February 27th
and will last 16 months. This project will cause traffic
delays. Please use an alternate route.
If you have any questions, Randy Cerchie at (239) 533-8580. |
 |
Three Oaks Parkway - The Three Oaks
widening project began December 4, 2006. The project will
widen Three Oaks Parkway between Corkscrew and
Alico to four
lanes and should be completed by September 2008.
If you have any questions, please
contact Randy Cerchie at 239/533-8580. |
|
Road / Bridge Maintenance |
 |
Signal work -6/26 Six Mile Cypress & Dani Dr.
Assistance of Ft. Myers PD
6/27 US 41 & South St - Assistance of Ft. Myers PD
6/30 US 41 & Briarcliff - Assistance of LC Sheriff
Expect delays from 9:00 AM to 3:00 PM |
 |
Matlacha Bridge
will have 15 to 20 minute traffic delays for repairs, Thursday,
June 26, 2008 from 8:00 p.m. to 2 a.m., one night only.
Contact Doug Busbee at 357-4674 for any
questions. |
 |
Treeline Av - Landscaping Arborwood Community
Development District will be managing the installation of irrigation
and landscaping along Treeline Av. between Colonial Blvd. and
Daniels
Pkwy. This project is scheduled to be completed by the end 2008.
Lane closures and traffic impacts may occur but will be minimal.
If you have any questions please contact David Wilkison at Wilson
Miller at 239-939-1020. Lee County DOT Operations will be consulting
when needed. You may contact Bob DeBrock at 239-694-3334 |
 |
Cape Coral Bridge - Lee County DOT Operations
will be managing the Steel Beams Repair and Painting for Cape Coral
Bridge Road (WB) over Caloosahatchee. The project will last for 120
days starting Monday, February 18, 2008. There will be lane closures
except for the peak traffic hours. There will be a reduction of 4
(four) feet to the clearance height due to the construction work.
If you have any questions,
please contact Ehab Guirguis at 239-694-3334. |
 |
There will be a road closure Wednesday, January 30,
2008 and Thursday, January 31, 2008 from 8:00 a.m. to 3:30 p.m. at
the intersection of Glenwood Avenue and Figuera Avenue,
intersection of Glenwood Avenue and Lynneda Avenue, and the
intersection of Glenwood Avenue and New York Drive in East
Fort Myers due to relocation of water lines (drainage and sidewalk
project for DOT). If you have any questions, please contact
Justin Dodd at 239-826-1454 or DeWayne Tagg at
239-357-1096 |
 |
Sewer Line Extension - 6535 Winkler
Rd ~ Lee County Utilities will be installing a sewer line
extension at 6535 Winkler Road on September 13, 2007, from
9:00 a.m. to 4:00 p.m. The lane closure will be the right lane
on the north bound side. If you have any questions, please
contact Rich Sims at 239-693-2992 x213. |
|
Clarys Site work will be
performing turn lane improvements on Burnt
Store Road just south of Embers Parkway during
the week of April 9th. Expect lane
closures during off-peak hours.
If
you have any questions, please contact Mike Tisch
at (239) 533-8110. |
|
County-Wide Road Resurfacing |
 |
Resurfacing
various streets countywide began June 4, 2008 and will
last for 12 months. |
|
County-Wide
Sidewalks Construction |
 |
Gunnery Rd Sidewalk - Construction of
the Gunnery Road sidewalk between 12th Street and
Buckingham
Road will begin on February 18, 2008, and should last 6
months. If you have any questions,
please contact Eyra Cash at 239/533-8562. |
 |
Glenwood Avenue - Construction of
sidewalk on Glenwood Avenue between Prospect Avenue and
Ortiz
Avenue began January 15, 2008, and should last 6 months.
If you have any questions, please
contact Eyra Cash at 239/533-8562. |
 |
Tice Street - Construction of sidewalk
on Tice Street between Ortiz Avenue and Lexington Avenue began
November 26, 2007, and should be completed by mid July.
If you have any questions, please
contact Eyra Cash at 239/533-8562. |